The Partners have already run different steps to fulfill all the expected objectives.
-
- The Kick off meeting was organized in Arese in September. All the Partners attended the event. It was a good chance to plan the activities to be done and to start the collaboration.
- The Partnership Agreement was approved by all Partners on December 2015.
- The public tenders schemes are ready and will be published according to the needs during the 1st phase of the project on the Italmatch website – Public Tender.
- The Dissemination plan is ready and the document has been shared among the Partners on January 2016.
- The first Progress Report has been submitted to EASME on may 16th 2016 and we are now waiting for the feedback (27/07/2016).
- The Notice Board was prepared and it will be exhibited at the Partners premises. It is also available in the Section “Deliverables and Reports” of the website.
- The second monitorig visit was organised on 10th February 2017 and the Mid-Term Report has been submitted to EASME on March, 16th 2017.
- The LIFE-Trialkyl Project was presented during the “Workshop on LIFE Programme”, organized by Federchimica in Milan on May, 30th 2017
- The Mid-Term Conference of the LIFE-Trialkyl Project was organized on June 27th 2017 in Arese. after the event, the participants visited the pilot plant at Italmatch premises.
- The LIFE-Trialkyl Project was presented during the international exhibition ”Ecomondo”, held in Rimini Fiera from 7th to 10th November 2017.